Site conditions:

  • Smoke was observed at the site but it is significantly less than in previous days

Activities:

  • Grading and other dirt work is continuing
  • Rip rap and other stones have been brought in for erosion control, primarily on the western slope
  • Approximately 158 truck loads of material from the borrow pit are planned to be brought to the site today