Site Conditions:
- No smoke observed on the site
- Odor can be detected at the top of the hill on the southern section of the site
Activities:
- Excavated area at the top of the hill on the southern section has been backfilled
- Grading and BMP installation and maintenance taking place, with fill material being brought in from the borrow pit
- 104 truckloads of material were brought in yesterday from the borrow pit, with about the same amount expected today